Thursday, September 30, 2010

3 Phase Electrical Service


REMC is here to bring the 3 phase service across the road. This is the first step in upgrading the electrical service. We will soon replace the transformer and complete the 3 phase service.


The weather is still wonderful. We haven't received any rain since the lumber package (with one slight exception)

Friday, September 24, 2010

Brick has begun



What a difference this will make compared to the vinyl siding that was originally there. The neighbors should be happy.

Tuesday, September 21, 2010

Here's the church, Here's the steeple...


This was an exciting delivery to receive!





It now will not be mistaken for a business. Looks great!




Friday, September 17, 2010

Slow progress at the sewer




We had the manhole delivered. We are pat all the utilities so it seems to be slightly faster than before. This is day 4 on Hoe Ramming.



The mechanical mezzanine is dry-walled and finished

Wednesday, September 15, 2010

Insulation, Drywall, Electrical and Plumbing begins


We are dry-walling the mechanical mezzanine to allow for installation of the mechanical units, ductwork, and schedule 40 sprinkler pipe


The studs and electrical boxes have been marked on the floor to insure that no electrical boxes are covered up and to have a visual of what is in the wall.



Still no rain in sight. 

Friday, September 10, 2010

Misc. Framing Complete


New steeple base is framed



New folding partition framing and font walls



Commercial tyvek installed



Straight shingle rows!!



This is really unfortunate. This is out 3rd day hoe ramming rock and we've only moved 15-20'. The operator was telling me how he's operated a Hoe Ram for years and can never remember getting into rock this hard. The good news is: The micropiles go 10' into this bedrock....It's not going anywhere!