A McClure Design and Build Project for The Church of Jesus Christ of Latter-Day Saints.
Monday, December 27, 2010
Sisal and EIFS
Sisal installed. It will be 32" to the top of the 4 1/2" chair rail that will be installed directly above the sisal.
The Mason's relocated their tent and the EIFS guys built theirs at the front to allow for EIFS installation under the arch and in the gable.
Thursday, December 16, 2010
Brick Almost Complete
We had to tent the front of the building to allow for brick progress. The brick has been laid up to the arch in the heated tent. The water has also been heated.
Fire Suppression System Riser Built
I had the Sub Contractor move the above main out and around to accommodate the steel ladder to be installed.
Drywall Finish and Paint!!
Drywall is complete. And painting is underway. The door frames will be primed today and the walls will be primed by tomorrow.
Tuesday, November 9, 2010
Wednesday, November 3, 2010
SOD!!!!
We exceeded the required topsoil depths throughout the site.
This will be the most beautiful detention pond this side of the Mississippi!!!
More brick work
Drainage structure in the pond
Tuesday, November 2, 2010
New Transformer and Topsoil
New 3 phase transformer set by electric company
Prep for drainage structure
Prepped and ready for seed/ sod