A McClure Design and Build Project for The Church of Jesus Christ of Latter-Day Saints.
Tuesday, February 15, 2011
Thursday, February 10, 2011
Tile Finishing Up!!
In the entrances there is a ceramic tile border that will get carpet squares in the center. The purpose of the carpet squares is that it gives a non-slip surface that can easily be changed when they become dirty without having to replace the entire area. (What will they think of next?)
Tuesday, January 25, 2011
Monday, January 24, 2011
Monday, January 17, 2011
Chapel Finishes!!
Next General Conference will be exciting on the new automatic projection screen
Recessed lighting installed and 3 out of 10 pendant lights installed. Let there be light
Thursday, January 6, 2011
Wednesday, January 5, 2011
Ceiling framing and ceiling tile
New ceiling tile in the existing hallway
Suspended metal ceilings installed in new classrooms
Chapel ceiling textured and painted
Monday, January 3, 2011
EIFS FINISHED!
The EIFS company was a joy to work with. They showed up when they said they would and finished when they said they would. Not to mention they did an excellent job. In other news, the brick continues...the visible line that you can see on the front of the building will go away after proper cleaning of the brick and mortar.
Monday, December 27, 2010
Sisal and EIFS
Sisal installed. It will be 32" to the top of the 4 1/2" chair rail that will be installed directly above the sisal.
The Mason's relocated their tent and the EIFS guys built theirs at the front to allow for EIFS installation under the arch and in the gable.
Thursday, December 16, 2010
Brick Almost Complete
We had to tent the front of the building to allow for brick progress. The brick has been laid up to the arch in the heated tent. The water has also been heated.
Fire Suppression System Riser Built
I had the Sub Contractor move the above main out and around to accommodate the steel ladder to be installed.
Drywall Finish and Paint!!
Drywall is complete. And painting is underway. The door frames will be primed today and the walls will be primed by tomorrow.
Tuesday, November 9, 2010
Wednesday, November 3, 2010
SOD!!!!
We exceeded the required topsoil depths throughout the site.
This will be the most beautiful detention pond this side of the Mississippi!!!
More brick work
Drainage structure in the pond
Tuesday, November 2, 2010
New Transformer and Topsoil
New 3 phase transformer set by electric company
Prep for drainage structure
Prepped and ready for seed/ sod
Tuesday, October 19, 2010
Wednesday, October 13, 2010
Asphalt
Greenbaum was here doing the appropriate testing as the asphalt was laid. All tests passed and there were no concerns about any aspect of the asphalt.
This is the area that we proposed fixing while we have equipment onsite. This was an old utility ditch that had sunken over the years. Craig and Ray approved this and asked it to be included in the job as a change order. McClure will not be responsible should this area continue to settle as we simply filled in the low spot as opposed to excavate and re-compact. I don't believe it will sink anymore anyway.
Asphalt is complete. The only thing left is to seal the existing lot. Ideally this would be done at the end of the project. The sealer plants close down at the end of October until Spring. We are still deciding whether or not to go ahead and seal within a couple weeks or to wait and return in March or April.
Tuesday, October 12, 2010
Spreading topsoil, hanging sprinkler pipe and asphalt prep!
Final grading for asphalt to be laid on wednesday morning
Spreading topsoil to the proper depths
Sprinkler pipe installed with the proper hangers
Friday, October 8, 2010
Doorframes, sprinkler pipe, brick and much, much more!!
Sprinkler pipe...at ease everybody, it's schedule 40!
Door frames
Brick at exisiting gable topped out
Existing handicap ramp removed in preperation for the new and improved handicap ramp with detectable, tactile warning!
Thursday, October 7, 2010
Sewer is hooked up
The sewer was air tested and hooked to the building. The Hoe Ramming ended last friday and from then until now it was straight digging. One more utility is finished.
Tile is underway. The font has been prepped with the appropriate waterproofing and will be tiled soon.