Monday, December 27, 2010

Sisal and EIFS


Sisal installed. It will be 32" to the top of the 4 1/2" chair rail that will be installed directly above the sisal.


The Mason's relocated their tent and the EIFS guys built theirs at the front to allow for EIFS installation under the arch and in the gable.

Thursday, December 16, 2010

Brick Almost Complete




We had to tent the front of the building to allow for brick progress. The brick has been laid up to the arch in the heated tent. The water has also been heated.


Fire Suppression System Riser Built



I had the Sub Contractor move the above main out and around to accommodate the steel ladder to be installed.

Drywall Finish and Paint!!





Drywall is complete. And painting is underway. The door frames will be primed today and the walls will be primed by tomorrow.